(first sorry for my english) i m entering a new value in the duration % comp field then i schedule but p6 doesnt update my new value.p6 hold my old value how can i solve this problem thnx
duration % comp doesnt update
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Ferhat,
Check activity type. It looks like Activity Type is "WBS Summary". P6 will never let you update the % of WBS Summary activity and it will bring % back when you reschedule.
Syed
Ferhat,
Had you set the activity as started by checking the check box beside started?
And are you a poweruser of the program?
Hi Ferhat
It seems that i cannot help you any further . Are you sure that you are displaying the correct column for "duration % completion"? You can check this by verifying whether the % completion in the status tab is the same as the display in the column you are using.
Maybe Raymund may have a solution
Regards
Johannes
Hi Johannes
my activity % completion type is duration.And i assigned baseline.i didnt add new activity or delete.but duration % comp doesnt change.i m checked the other projects on p6.on my project "Link Budget and At completion for not started activities"
is not active and i cant mark it maybe problem is here?
Hi
Ferhat
There are several reasons why the updating of the duration % completion are not showing.
Regards Johannes