Computing Actual cost for activities under progress

Hi all,

I am updating a schedule with some resources assigned. When I update activiites which have started but not completed, I dont get the actual cost after scheduling(F9). I have to go to  Tools --> Recalculate Assignment Cost to see my actual cost update for the activity.

Is there any setting I have to do to calculater this cost automatically after scheduling.

Note: Actual cost is computed for completed activities but not for the ones in progress.

Thanks ,

Sendhil

 

 

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts