Wronge start / finish date

S
Samer Hozin 👤 Member for 15 years 5 months

I set the project calender to 12 Hrs/ Day 7 Day/weeks and also the admin user pereference to 12 Hrs / day and check all user to specify the number of hous for each time period .

my problem is when I try to make - 6 hours lag for an activity it give me wronge start date for it

for example the activty by default start at 21 spep. 2PM and after assign -6 Hrs alg it start at 19 sep 10 AM ?

S
Samer Hozin 👤 Member for 15 years 5 months

Sir

thank you for the replay

I assign lag because i want to start the successor activty late by 6 hrs before other activity finsh and sure it FS also the project calender is 12 hrs / day 7days / week and not link to globe calender , so why this happens

M
Mike Testro 👤 Member for 20 years 6 months

Hi Samer

Welcome to Planning Planet.

Why are you applying peculiar lags anyway?

The correct linkage should be Finish Start between all tasks and that will solve your problems.

21st September 2012 is a Friday so maybe you are linking back across an Islamic weekend.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts