Schedule percent complete

N
Naseer Yama 👤 Member for 13 years 10 months

             

A
Andrew Tan 👤 Member for 21 years 8 months

Hi,

I believe,

Schedule percent complete is based on planned progress which is your baseline.

If you want to compare baseline and current schedule, this should work.

 

Thanks,

I
Irfan Khan 👤 Member for 16 years 11 months

welcome Naseer,

the Schedule percent complete is equal to your planned progress.

 

regards,,,,

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts