Hello Planners,
Question for you guys. I am used to MS Project where I could Save As to multiple versions of the plan as I was playing with the dates in the plan.
1) With PV, I know I can baseline to take a snapshot of the plan. Is there another way to take a snapshot and restore incase my "Schedule" ends up changing dates I didnt intend to change?
2) Need to research this but, is there a clean way of restoring Baseline plan (including additional task, resources etc) as the current plan?
Thanks,
Riz
Dont know if its the best way, but I copy/paste the project in the EPS.
Haakon
Note, I should say "The Best Way to version", not "Only". I am hoping to learn the best way and not just other options that one would not really use.
Thanks.
Riz