hi to all experts, i am currently running cost loaded schedule. Problem : while updating the schedule, when i am going to put % to my activity jst after checking the Started Box my Budgeted Cost Column is going to be "0" Zero. Just because of this i have to put again my all values manually n still m facing the same problem. need help guys....thnx