Hello,
I looking for a solution concerning primavera P6.
I wonder know what is the link between baseline activities & the current planned schedule, I mean not the link like SS, FF, etc, but is the criteria (field) used by the activity in the baseline to recognize the activity in the current planned schedule.
For example in P3 it was the activity ID, but in P6 it seems not to be the same. Indeed when you change the activity ID of an activity, the baseline remain and don't desepear like in P3.
Does anyone has the clue?
Thanks a lot
The Baseline will disapear aftyer renumbering when you press F5 to refresh.
The planned dates are a disaster and should be avoided. I have an article under Technical Papers on my web sites titles "What Baseline Bars am I displaying" which explains some of the issues with these dates. I suggest you consider have a read ot it.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.eastwoodharris.com
www.primavera.com.au - a Primavera scheduling software resources site