I have level of effort activities with resource assignments.
I have noticed that LOE’s that are in progress have the Late start date set equal to the Actual start date. This causes remaining late work to show up before the data date on histograms.
Is that a P6 bug ? Is there a way to solve this issue ?
Thanks
Sue
Susan, there is not eniough information to understand your issue. It has been my experiance that P6 does not always calcuate negative dates correctly, but on the other hand you many be caught up by the dreaded "Planned Dates" issues.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.eastwoodharris.com
www.primavera.com.au - a Primavera scheduling software resources site
Will really appreciate some feedback.
Thanks