Hello Planners,
I had an issue with the update progress.
When i do update progress as on 31st Aug 23:59 actuals should be applied to all the activity started before 31st Aug 23:59 but i am facing a problem with this no actuals are applied.
Can anyone solve my query?
Thank you
Regards,
Rajesh.
If you are not mannually Updating the Resources then make sure that "Auto compute actuals" option is checked.