Cost Data no Importing Properly

Contractor has submitted an updated schedule and the cost data (Budget at Completion or Budgeted Cost) for newly added activities is importing incorrectly. The contractor sent me a screenshot of his activities and I can see the correct costs. Yet when I import the file, the costs reset themselves to either $8 or $40. 

I have received numerous other schedules from this particular contractor in the past and have not had this issue. I have received updatse from other contractors and have not had this issue. It leads me to believe that there is a setting or bug somewhere. The contractor is using version 7.0 and I'm using 8.1. Any suggestions would be helpful. 

 

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts