Primavera P6 WBS Summary Man-hour allocation

Hello,

I have a question on how best to load in budgeted and actual man-hours into my P6 schedules.  I plan to do this using a WBS Summary Activity as a majority of the schedule activities are milestone but I need to track the total hours that are charged to specific WBS charge codes.  What is the best way to accomplish this task?  Any information would be appreciated as I have just started using P6 and would like to adapt form using P3.

Thank you
Christy

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts