My client wants me to submit a three week look ahead using the following format. I was wondering if anyone can help me create it in P6. Thank you in advance
My client wants me to submit a three week look ahead using the following format. I was wondering if anyone can help me create it in P6. Thank you in advance
You can'tcreate that in P6 -You can only display baseline/planned/actual dates in columns and not rows.
You'll have to export the data to excel, and then juggle it around into the right format.