Finish date problem

Hello,

I have just updated a plan with new start and finish dates.

On one activity i have changed the start date but i'm unable to change the finish date to the new required date. The new finish date is just 2 days more so i changed the duration by 2 but that didn't give me the required date.

Any suggestions please

Thanks

Richard

R
Richard Brown 👤 Member for 14 years 6 months

Raymund,

I'm sure i tried changing the remaining duration but i will try again on monday.

I don't understand why this one activity won't let me just enter the new finish date, could it be a constraint?

Thanks for your reply.

 

Richard

R
Raymund de Laza 👤 Member for 16 years 6 months

Richard,

In an updated activity, if you change the Original Duration then the finish date will not change. Try changing the Remaining Duration so that Finish date will change.

Hope this will help.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts