Hello,
I have just updated a plan with new start and finish dates.
On one activity i have changed the start date but i'm unable to change the finish date to the new required date. The new finish date is just 2 days more so i changed the duration by 2 but that didn't give me the required date.
Any suggestions please
Thanks
Richard
Raymund,
I'm sure i tried changing the remaining duration but i will try again on monday.
I don't understand why this one activity won't let me just enter the new finish date, could it be a constraint?
Thanks for your reply.
Richard
Richard,
In an updated activity, if you change the Original Duration then the finish date will not change. Try changing the Remaining Duration so that Finish date will change.
Hope this will help.