Theoric Duration % complete

Hi all

Since months ago I have this issue in mind but I did not discover this site till yesterday. It seems there are a lot of pundits here so sure my question will get solved. Here I go.

Let's say that I have an activity in both in the project and in the baseline. This activity was planned to start in the past but it has not started. Hence, the physical % completion is obviously 0. How can I see though the theoric Duration % Complete based on the dates in the baseline?

Thanks in advance,

Frances.