Global Change "Total Cost"

J
Jenny Ingco 👤 Member for 14 years 4 months

Dear All,

 

How I can use the Global change to change the "At completion total cost" ??

 

Thank you,

 

HANSON

A
Arend Woltjer 👤 Member for 14 years 8 months

Hi hanson,

 

at completion total cost is the sum of at completion expenses, lobor, non-labor and material cost.

So you have to change 1 of those 4 elements.

For example like this:

I hope it answers your question,

Arend

 

 