Progress Line

Is it possible to update / move the progress line without showing the actual progress (spotlight progress). i.e to turn the spotlight off.

I don't want to re schedule, just change the data date without showing the spotlight.

 I am using P6.v7

Thanks

M
Mabis A 👤 Member for 14 years

I am using P6 ver.6.2 : just change data date in "dates" tab in the project detail . dont press F9 if you dont like schedule your plan based on new DD.

Regards,