Is it possible to update / move the progress line without showing the actual progress (spotlight progress). i.e to turn the spotlight off.
I don't want to re schedule, just change the data date without showing the spotlight.
I am using P6.v7
Thanks
Is it possible to update / move the progress line without showing the actual progress (spotlight progress). i.e to turn the spotlight off.
I don't want to re schedule, just change the data date without showing the spotlight.
I am using P6.v7
Thanks
Thanks got it now.
I am using P6 ver.6.2 : just change data date in "dates" tab in the project detail . dont press F9 if you dont like schedule your plan based on new DD.
Regards,