Hello Planners,
Is there an easy way to delete all relationships from a schedule in P6.7. I used to do it with global change in P3 but it doesn't works in P6.7 !!!
P6.7 global change is not efficient !!
Regards,
Aymen
Hello Planners,
Is there an easy way to delete all relationships from a schedule in P6.7. I used to do it with global change in P3 but it doesn't works in P6.7 !!!
P6.7 global change is not efficient !!
Regards,
Aymen
Because P6 does not gives the user direct access to any relationships table as other software do you can explore the use of Logicleague By Ron Winter as a way to overcome this limitation.
http://scheduleanalyzer.com/ll_brochure.htm
Will not be as easy and powerful as if implemented within the software itself but you will be able to do more things others are used to, like being able to switch on and off relationships and very common things like filter for float and deleting all relationships at a single click of the mouse.
duplicate ... see above
Hi Mike,
I am using Excel to edit quickly the relationships, I used to do it in P3 without facing any problem but I have to delete all the relationships before importing excel data (by doing a global change in P3).
Many thanks,
Aymen
Hi Aymen
Why would you want to delete all the links?
It seems a daft thing to do.
Best regards
Mike Testro
Hi SM PUM,
Thank you for your reply.
I am looking for a way to do it without creating a new project.
Regards,
Aymen
Aymen BEN YOUSSEF
Salam To u Aymen.
Not a big issue.Copy ur project in project window and then paste their.Just check of the option of Resources during coupying.
Regards