Revised baseline having two different schedule percent complete for the same data date

Hi Everybody,

The MBSL was prepared and approved before 2 years & it worked fine. Recently my Master Baseline schedule (MBSL) was asked to revise due to Extension of Time. I revised my MBSL by inserting new milestones & corresponding links also been changed.

Now my Problem is, when I start to update i get 2 different schedule percent complete for the same data date.

ie., on extracting the monthly cashflow in revised baseline I computed the monthly planned value. when I attach it to the updated schedule with actuals by making a copy of revised baseline report I get different value, not as same as planned value obtained through cash flow. But i hope it should match

There was no change in resource assignment only links have been changed.

Please help me to fix this issue

 

Best Regards,

Akbar

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts