Hi I have just imported some resources , I imported budget cost only. The problem is that all the resource durations have set themselves to zero and dates don't match activity dates. Any ideas on what setting I ma have wrong ?
Thanksb
Rob
Hi I have just imported some resources , I imported budget cost only. The problem is that all the resource durations have set themselves to zero and dates don't match activity dates. Any ideas on what setting I ma have wrong ?
Thanksb
Rob
Hi Rob,
Did you try to go Tools-Level Resources ? If not please, try to do it but, after you make a copy of your schedule and let me know if it's work with you?
Thank you,
HANSON