Activity task bar

Hi,

I need to show all completed tasks in blue on the activity task bars.

I'm not sure which name bar to choose / add to, the only relevent name is 'Complete %'!!

Any advise would be appreciated.

 

Richard

G
Gary Whitehead 👤 Member for 17 years 2 months

 

You need a bar with the timescale set to "Actual Bar"

 

The default bar name for this is "Actual Work"

 

Cheers,

G