P6 Calculation of actual units/costs

Can anyone out there explain why P6 (7.0) doesnt alway calculate actuals....?????

[[wysiwyg_imageupload:1034:]]

This is driving me crazy! 

Yes, auto compute actuals is ticked on and costs are calculated from Units

 

 

A
Andy McShane 👤 Member for 22 years 8 months

Thanks Alexandre,

 

I have every possible option of auto compute actuals turned on, both at activity level and resource level.

Cannot find an option for this at project level.......

A
Andy McShane 👤 Member for 22 years 8 months

Thanks Alexandre,

 

I have every possible option of auto compute actuals turned on, both at activity level and resource level.

Cannot find an option for this at project level.......

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Andy,

did you tick Autocompute Actuals at project level?

check your resources, Autocompute should be ticked on there too

Alexandre

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts