Import form excell, WBS lost

I have exported to excelll the activity details such as ID, Name, dates, % Complete etc. But once you import those updated data back to P6 file it losing the entire group and sort.

WBS dictonary remains unchanged but group and sort does not work. Is any body is having the same problem.

Regards

Santhosh

A
Alexandros Kroustis 👤 Member for 19 years 5 months

Did you exported from a project and trying to import to another copy of the same project (or renamed the id of that project)?
If yes you need to replace the old project id with the new in your excel.
For example, if the id of the project you exported is "proj1" and you are trying to import to a project with id "proj2" you need to replace "proj1" with "proj2" in your excel, save it and then import.
If you take a look wbs starts with project id.

A
Alexandros Kroustis 👤 Member for 19 years 5 months

Did you exported from a project and trying to import to another copy of the same project (or renamed the id of that project)?
If yes you need to replace the old project id with the new in your excel.
For example, if the id of the project you exported is "proj1" and you are trying to import to a project with id "proj2" you need to replace "proj1" with "proj2" in your excel, save it and then import.
If you take a look wbs starts with project id.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

yeah think I said that NEVER change ANY column names that yo uhave exported 

B
Baykan Yigit Sogut 👤 Member for 6 years 10 months

While exporting Activity Sprea Sheet into Primavera, you shoudl always keep WBS Column as shown below.

[[wysiwyg_imageupload:6940:]]

Z
Zoltan Palffy 👤 Member for 16 years 10 months

3 possibilities here 

possibility #1 you removed the wbs_id column

If the WBS Code (wbs_id) column is removed from the Excel spreadsheet entirely the activities will be moved to the root WBS which is the higest level of the wbs

Possibility #2 If there are spaces at the end of the WBS code in Primavera, Excel then truncates the spaces and then Primavera cannot recognize the WBS code as an existing code. So Primavera assigns those Activities to the highest level WBS code.



In order to fix this from Project Management, browse to Project, then WBS   and then remove any spaces that are at the end of the WBS code.



For a simple way to process this, select any WBS Code, then go to 

Edit, Replace:

"Find what:" hit the spacebar once to show a blank space.

Leave "Replace with:" empty to remove all the spaces.

Click "Replace All".

Possibility #3 f you export a column that will compile a list, and this list has a column of more than 100 characters then the characters after the 100th character are cut off

these are the only way that I can see this happening. 

S
Sandy Meza 👤 Member for 6 years 10 months

SAME ISSUE CONSIDER THAT the excel file comes with the WBS asign by default, and even though I lose the Wbs asign to each activity, any help please?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

yeah the solution is to also export the wbs in the 1st place. JUst group and sort again

Z
Zoltan Palffy 👤 Member for 16 years 10 months

I am not sure how you did this because you CAN NOT export any information to excel without also exporting the wbs code.

are you saying that the wbs is no longer assigned to the activities but the activity structure is intact ? 

A
Anil Varghese 👤 Member for 12 years 2 months

Yes; I have exported to excelll the activity details such as ID, Name, dates, % Complete etc. But once you import those updated data back to P6 file it losing the entire group and sort.

WBS level of activities gone!! Please help

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts