Calculated Field

Can anyone tell me how to create a calculated field (like MS Project) in global change that will recaluate automatically (example as with BL Variance) so I do not need to recalc F9 every time. Thanks

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello,

there is no such calculated fields in Primavera P6 client; you have to run global change to get the result

or have a look at Primavera Web client calculated fields

Alexandre