Can anyone tell me how to create a calculated field (like MS Project) in global change that will recaluate automatically (example as with BL Variance) so I do not need to recalc F9 every time. Thanks
Calculated Field
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
thanks Andre this is what I expected
Hello,
there is no such calculated fields in Primavera P6 client; you have to run global change to get the result
or have a look at Primavera Web client calculated fields