Baseline Target Schedule

I am using P6 V6.2. When I create a baseline using Create from Current Schedule it is not saving the latest / current schedule. Every month I need to generate snapshot target or new baseline of this month status. We use this to measure variance between each progress update. Is there a trick? (I was able to do this all the time with V7). Is there a toggle that I need to turn on/off?

R
Ron Beechey 👤 Member for 24 years

Mary

Under Admin Preferences tab Earned value under Earned Value Calculations make sure you have "Budgeted values with current dates" selected.

 

Hope this also helps

D
Daniel Limson 👤 Member for 24 years 8 months

Hi Mary,

To create a baseline, go to projects then follow this sequence, Maintain basleine, Assign baseline and then go to your Bars icon and tick either your primary or secondary baseline bar depending on what you need to see.

Regards,

Daniel

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts