Activities Relations

J
Jenny Ingco 👤 Member for 14 years 5 months

Dear Schedulers,

I have WBS and the all activities in it are FS relations so, each one should start dierect behaind the processor is finish. But what happend I have gab now beteen two activities 20 days as far as the relation is FS. So, any idea why that's happinig?

 

Thank you all

F
Frederic Fasquelle 👤 Member for 20 years 3 months

Hi Hanson,

This gap could also be created by some predecessors not marked as "completed" and linked in FS to your current.

You could also have a look inside your Primavera log report, in chapter "Errors".

Regards

R
Ronald Winter 👤 Member for 23 years 5 months

Hanson,

This gap is probably due to the activity’s calendar.  Look for a vacation period.  Otherwise, look for lag values in the relationships.  Good luck!

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts