Dear Schedulers,
I have WBS and the all activities in it are FS relations so, each one should start dierect behaind the processor is finish. But what happend I have gab now beteen two activities 20 days as far as the relation is FS. So, any idea why that's happinig?
Thank you all
Hi Hanson,
This gap could also be created by some predecessors not marked as "completed" and linked in FS to your current.
You could also have a look inside your Primavera log report, in chapter "Errors".
Regards
Hanson,
This gap is probably due to the activity’s calendar. Look for a vacation period. Otherwise, look for lag values in the relationships. Good luck!