Differencies between Actual units in Activities sheet and tracking sheet (Resource Allocation)

Dear planners,

I am getting a problem regarding actual unit & budgeted unit.

As it can be seen in below snapshot of activities sheet in primavera 6, the actual non labor unit is set to be 104650 which is same as actual cost since I assign 1$/hour for price /unit. 

activity.png

But in tracking sheet as it shown in below pictures the actual unit or cost is totally different from what is shown above or with the budgeted unit.

tracking.png

 

As it shown all days actual are the same as budget except 3 latest days and cum. actual unit is different from what is shown in activities sheet.

 I put the data date to 29 oct 2011 17:00. My calendar for both resource and activities is 7 days’ workweek.

Anybody can help me to understand why this occurred and what can I do for it is most welcome and appreciated.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts