Compare the progress vs baseline based on Duration concept in P6 as in P3

Dear All,

How can I compare the progress vs baselinein P6 based on the duration concept as we used to do in P3.

In other words to calculate and rolling up the % progress based on the summation of executed durations divided by the summation of total durations .

Thanks and Regards,

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts