show progress bar on baseline

K
kp rao 👤 Member for 14 years 10 months

Hi,

I assigned a baseline with progress to the current project.The baseline update is one month before the current project.

I want to show progress bar on baseline.

1.I want to show baseline progress percent complete in the current project.That is two bars are there.One is current bar with current progress and baseline bar.I want to show baseline progress bar.

2.Show current progress on the baseline bar.

Schedule percent complete bar is not as baseline percent complete.I dont want to show schedule percent complete.

Urgent help please.

kp

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

So simple... transfer the row of progress bar in the same row of the baseline bar.

Apply a different pattern and color.

Hope this will help.

A
Abdullah Merchant 👤 Member for 15 years 6 months

Hi Kp,

Are you saying that you want to show your Baseline bar and then show a separate bar above it that shows your actual progress? Because thats easy..............actually i have a little diffculty in understanding what you mean by baseline progress bar.....beacuse showing how far you have gone is tobe compared against your baseline and im sure youre aware of that it but showing the progress in your baseline is new for me too...

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts