Greetings,
Im having a tough time understanding the Budgeted Cost being wrongly dispalyed for an Activity which has a resource as follows:-
- The Activity is 10 days in duration and set to " Fixed Duration and Unit"
- The Activity and its Labor Resource"XYZ" both share the same 6 Days a week and 8 hours a day Calendar
- The Labor Resource "XYZ" has a Price/Unit of Rs.100/hour
- Only 1 Unit of Labor Resource "XYZ" is scheduled for each of the 10 days that make up the activity
So the Budgeted Cost of the Activity should be= Rs.100/hour X 8 hours (each day) X 10 days = Rs. 8000
But my Budgeted Cost adds up to Rs. 1000..........thats it...........what am i missing????
Thi