Wrong Budgeted Cost Calculation

Greetings,

Im having a tough time understanding the Budgeted Cost being wrongly dispalyed for an Activity which has a resource as follows:-

  • The Activity is 10 days in duration and set to " Fixed Duration and Unit"
  • The Activity and its Labor Resource"XYZ" both share the same 6 Days a week and 8 hours a day Calendar
  • The Labor Resource "XYZ" has a Price/Unit of Rs.100/hour
  • Only 1 Unit of Labor Resource "XYZ" is scheduled for each of the 10 days that make up the activity

So the Budgeted Cost of the Activity should be= Rs.100/hour X 8 hours (each day) X 10 days =  Rs. 8000

But my Budgeted Cost adds up to Rs. 1000..........thats it...........what am i missing????