baseline

hi my friends

how can i make import or export in p6 without loosing the baselines

because every time when i made export from p6 i lose the baselines

with best regards

mahmoud el shamy

M
mahmoud el shamy 👤 Member for 14 years 4 months

dear ranjiv kurup

thaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaank you 

i cant describe the words

i am really really thank you

eng mahmoud el shamy

R
Ranjiv Kurup 👤 Member for 15 years 4 months

Create a copy of the current baseline.

Restore the copy.

Export the restored baseline copy with project.

 

To import:

Import both projects (XERs).

Use the "Convert another project to a new baseline of the current project" feature.