hi my friends
how can i make import or export in p6 without loosing the baselines
because every time when i made export from p6 i lose the baselines
with best regards
mahmoud el shamy
hi my friends
how can i make import or export in p6 without loosing the baselines
because every time when i made export from p6 i lose the baselines
with best regards
mahmoud el shamy
dear ranjiv kurup
thaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaank you
i cant describe the words
i am really really thank you
eng mahmoud el shamy
Create a copy of the current baseline.
Restore the copy.
Export the restored baseline copy with project.
To import:
Import both projects (XERs).
Use the "Convert another project to a new baseline of the current project" feature.