PDF format problem

Hi,

I need to produce my schedule in PDF format but the start and finish columns are showing part of the time after the date on my printout (i only require the date and not the start / finish time)

I have used the column sliders to just show the date on the schedule but when i Pdf the plan part of the time appears after the date.

Thanks in advance.

Richard.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Richard,

it looks like a memory problem between Primavera and your PDF software

1. to display date without the time, go to Edit, User Preferences, Date and turn off the time display

2. make sure to display the columns you want to be printed and no others in the Gantt Chart columns: withdraw the unwanted columns and / or hide the rightmost columns by sliding the chart to the left

3. in the page setup, options tab, uncheck the "All columns" option

4. if this does not work, try to use another PDF software

Regards,

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts