If your question was how to get a Activity Report Layout report (Predecessor and Successors) where there is a Layout format (Group by WBS, Activity Codes... etc), that is possible in P6.
An example is shown below (group by WBS)[[wysiwyg_imageupload:906:]]
Maybe you need to re-phrase your question, but anyway to give you an idea on relationships and lags
Types of relationship in a Precedence Method
Finish to Start Relationship [[[[[[[1st[[[[[[[[[[F ---->S[[[[[[[[2nd[[[[[[[[[[ (2nd activity can only start when 1st activity is finished) now you can put a lag (+/-) and it would mean 2nd activity can only start (if you put 2 days lag) 2 days after 1st activity is finished
Start to Start Relationship S[[[[[[[[1st[[[[[[[[[[ --->S[[[[[[[2nd[[[[[[[[[[ ( 2nd activity can start in parallel with 1st activity) if you put a lag of 6 days then 2nd activity can only start 6 days after the start of 1st activity
Finish to Finish Relationship [[[[[[[1st[[[[[[[[[[[F ----> [[[[[[[2nd[[[[[[[[[F (1st activity must finish before 2nd activity can finished. if you put a lag FF with 1 day lag, the 2nd activity will finished 1 day after 1st activity is finished.
Start to Finish Relationship S[[[[[[1st[[[[[[[[[ [[[[[[[2nd[[[[[[[[[[F (1st activity must start before 2nd activity can finished)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
If your question was how to get a Activity Report Layout report (Predecessor and Successors) where there is a Layout format (Group by WBS, Activity Codes... etc), that is possible in P6.
An example is shown below (group by WBS)[[wysiwyg_imageupload:906:]]
Dear,
Unfortunatlely you cannot get the relationship type and lag in any of the layouts.
you can only get it by exporting to spreadsheet format.
while exporting it to excel use the subject area as activity relationship instead of activity in the modify template.
cheers
Muhammad,
Maybe you need to re-phrase your question, but anyway to give you an idea on relationships and lags
Types of relationship in a Precedence Method
Finish to Start Relationship [[[[[[[1st[[[[[[[[[[F ---->S[[[[[[[[2nd[[[[[[[[[[ (2nd activity can only start when 1st activity is finished) now you can put a lag (+/-) and it would mean 2nd activity can only start (if you put 2 days lag) 2 days after 1st activity is finished
Start to Start Relationship S[[[[[[[[1st[[[[[[[[[[ --->S[[[[[[[2nd[[[[[[[[[[ ( 2nd activity can start in parallel with 1st activity) if you put a lag of 6 days then 2nd activity can only start 6 days after the start of 1st activity
Finish to Finish Relationship [[[[[[[1st[[[[[[[[[[[F ----> [[[[[[[2nd[[[[[[[[[F (1st activity must finish before 2nd activity can finished. if you put a lag FF with 1 day lag, the 2nd activity will finished 1 day after 1st activity is finished.
Start to Finish Relationship S[[[[[[1st[[[[[[[[[ [[[[[[[2nd[[[[[[[[[[F (1st activity must start before 2nd activity can finished)
Best regards,
Daniel