Completion and start dates on P6 schedule

Hi,

For some reason the P6 installed on my laptop calculates start date as finish date completes.  For example:

Activity 1, Duration 4 days, Start January 2, 2012, Finish January 5, 2012 

Activity 2 Start must be January 6, 2012 since it's successor to the Activity 1, but the Activity 2 starts on January 5 same as finish date of .  This is happening on entire schedule.  I have checked User Preferences, and the Calender settings but i cann't understand where the problem is coming from.  Any idea?

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

Set the Working Time on your calendar and also show the time on the dates columns to be able to see the problem.

Hope this will help.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts