So I am ready to make my first update of the schedule in P6. My current data date is January 15th and I need to shift it to January 31st. I have collected actual and new forecast dates for the activities within that period and I would just like to know how you guys do your updates in P6. Do you shift the data date first and then you enter the actual and forecast dates OR do you enter the actual and forecast dates first, and then you shift the data date? What option(s) do you use for this or what series of steps you follow to do a proper update and shifting of the data date in P6? Thanks in advance for all the replies.
How do you update the schedule in P6?