Original duration

[[wysiwyg_imageupload::]]

Dear All,

 

I have to update a Schedule but I am having a problem updating the original duration. In the image above for exemple in the activity "Planejamento" the Original duration is 37d but I need to change it.

Should it be the sum of the sucessors activity? How it is calculated? 

 

Look the image below

primaveracsn.jpg

M
Marwan Hmood 👤 Member for 14 years 7 months

37 days, calculated from earliest activity start and finish dates. Updating summary OD must be done through updating activity OD.

 

Regards,

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts