Time Setting for Two Different Team

J
John Peter 👤 Member for 15 years 2 months

Oh Hi guys 

 

I hope you have completed your Xmas shopping ....

I have a small team of civil designer and site team of workers

civil designers mostly work in office and they do 37.5 hr per week 

where as site staff do 40 hrs per week 

if i change time period to 37.5 hr per week in primavera than my site 8 hours activity shows me duration like 1d.5hr

and 40 hours as 5d2.5hr 

 

Any suggestion on this Issue

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts