I have a small team of civil designer and site team of workers
civil designers mostly work in office and they do 37.5 hr per week
where as site staff do 40 hrs per week
if i change time period to 37.5 hr per week in primavera than my site 8 hours activity shows me duration like 1d.5hr
and 40 hours as 5d2.5hr
Any suggestion on this Issue
Try creating two different resource calander one with 37.5h per week for civil designers and other 40h per week for site team. Assign these calenders to their respective activities. You should also set activity type as resource dependant and appropriate duration type either fixed units or fixed units/time.
Cheers
John,
I use different software but try using a 24/7 calendar for your Civil Designers, then assign a 37.5 hours per week calendar to your Office Design activities and a 40 hours per week calendar for your Site Design activities.
By assigning a 24 hours 7 day per week calendar to your resource you will be able to assign different work hours to the work at the office and work at the field to the same designer.