Cost Loading

V
V Kutty 👤 Member for 15 years 4 months

Hi,

I am trying to resource/cost load a project.

I have 5 activities in various WBS that have 1 total cost. So I was told to use a level of effort and load the cost and resource onto the level of effort. This is exactly what I did. However, when I look at the loading curve of the LOE it loads the whole cost within the first month of the 6 month activity.

Does anyone know why this happens or how this can be fixed?

Thanks,

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi

Suggest to use WBS summary task and take the tab expensen and use uniform spread over te wbs summary. Assume yoy use P6

Johannes

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts