Fixed Units Duration type

S
shima memar 👤 Member for 14 years 5 months

Dear friends

I’m planning for a manufacturing company which manufactures Steel Structures. Here is description of what I should plan:

Column: 200 ton

Stairs:  400 ton

Handrail:  500 ton

I defined the amount of ton as the budgeted Units of resource for the above activities. Should I define duration type as “Fixed Units”  ? and set the calendar to resource calendar? I mean resource dependent activities?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts