Auto compute actuals ?????

 

Dear Friends

I have a question about the above subject.

The function "Auto compute actual" under the details tab in resource workspace didn’t work when I put the function” Recalculate Actual Units and Cost when Duration % Complete Changes" checkbox on under calculation tab in project workspace.

I can’t understand the differences between these two options 

 

Regards

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Yâser,

"Recalculate Actual Units and Cost when Duration % Complete Changes" means that P6 will calculate resources actual work when you enter actual % duration in the status tab 

"Auto compute actual" at the resouirce, resource assignment or activity level means that P6 will calculate actual work for the resource when you are using the Tools, Apply Actuals feature.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts