Updating the program

Dear Friends

After updating my base program .There is a delay of 29 days & it is showing only in the program.

But in the activities the maximum negative float is -25 only .Any one resolve this issue.....???

 

I will attach the picture

updation.jpg

D
D Artagnan 👤 Member for 17 years 8 months

I had the same problem. IMO, if it's a milestone, use the 7 day calendar.

A
Arun Vasanth 👤 Member for 16 years 7 months

Thank you Mohamed 

 

In my Base program there are 2 calendors .

1.6 day Calendor 

2. 7 days calendor 

Which one I have to make as default????

M
Mohamed Sallam 👤 Member for 19 years 10 months

Arun,

In order to avoid the difference, you may assign the Project calendar as default global calendar.

To calculate delays, you should consider the difference between working days and calendar days.

The variance - BL Project finish date should be considered, in that case the delay is 29 calendar days.

Did I clarify your queries?

A
Arun Vasanth 👤 Member for 16 years 7 months

Thank you Mohamed 

 

Then For making one what I have to do????

I have to consider the actual delay as 25 or 29 days???

N
Nithin Shetty 👤 Member for 21 years 9 months

Thanks Mohamed. This is of my interest too. Is there a way to show overall total float in the same project calender? Please advice. 

e.g. it shows -25 instead of -29.

Thanks.

M
Mohamed Sallam 👤 Member for 19 years 10 months

Arun,

This is due the difference between the global and project calendars. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts