Error with labor units

D
dinh khanh 👤 Member for 14 years 7 months

Hi all,

I'm very new to P6, so I'm sorry if my question is a stupid one or be duplicated.

When I change the duration parameter as the following figure (80% in this case):

p6_cost_error.png

The trouble is raising with Labor Units:

Their budget was set as 640

With the change of duration, my expectation is the remaining should be: 640 - 512 = 128 instead of 320 as you see.

How can I overcome this trouble?

 

Thanks for your support.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts