Flaws in P6 – Setting an ongoing program as Baseline

Dear All,

Why P6 can’t shows correct dates of Start and Finish (BL Start & BL Finish), if we set an ongoing program as baseline program. When we insert baseline column of an ongoing program, most of the activities, which are already completed are showing different dates. The problem can be solved by inserting a column called BL Actual start and BL Actual Finish. But when we insert these two columns, the forthcoming activities cannot be seen? How to solve this problem.

regards,

 

Haresh Jayanth - PMP , PSP

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts