Moving Activities Between Projects

K
Kris Durbin 👤 Member for 14 years 7 months

**

H
Hannes de Bruyne 👤 Member for 20 years 10 months

Hi Kris

 

what Shahul said is a very good option. Open all Projects, Change to the WBS-view and shift single branches to the required project (Right mouseclick on the very left side of the text-line)

Another way is cut and paste instead of copy and paste (Ctrl-x, Ctrl-v), links will remain, activities or WBS-Branches are shiftet to the right project

R
Rafael Davila 👤 Member for 22 years 3 months

Consider using Project Portfolios, the details are software specific and I use other software but this shall be the way to go.

Good luck,

Rafael

S
Shah. HB 👤 Member for 17 years 6 months

Hi Kris Durbin

In P6.7 you have an option to move WBS between projects which helps to fix your issue

 

Regards

Shahul

M
Mike Testro 👤 Member for 20 years 5 months

Hi Chris

If I were doing this in Asta PowerProject I would set up the first two projects and add the inter project links - I assume these are standard for each project.

I would then copy these two to make four projects and again set up the inter project links tp make a block of four.

By copying and pasting these blocks from four to eight to sixteen etc it will not be long before the whole set is linked up.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts