I have the 'calculate costs from units' clicked on to calculate the remaining costs. The problem I have is that this also calculates the actual costs which I do not want to happen. Is there a way to only calculate the remaining costs by units and for P6 not calculate the actuals costs from units.
Require Remaining Costs Calculated but not Actual Costs