I have loaded my P6 schedule with 17 resources and I have entered "planned" units resource numbers for each resource/each activity.
When I pull up the resource graph, the planned units only show up in the first month (for example: 3 month activity with 96 hours... all 96 hours are in month one).
I know this is a setting somewhere. I've searched, but no luck.
Thanks! Bill
"You can try setting the "Resource Units/Time" for each activity to a value that gives you an even spread over the duration of the activity. You can add a column "Resource Units/Time" column in your Resource tab. You will have to provide a value for each resource in each activity. "
I'll be trying that on Monday morning... That was also recommended by a co-worker, but I didn't have a chance to try it today. To busy!!!
Thanks for your help!
Bill................
Hi Bill
Check the histogram is for selected activities or for all activities
Cheer's
Shahul
You can try setting the "Resource Units/Time" for each activity to a value that gives you an even spread over the duration of the activity. You can add a column "Resource Units/Time" column in your Resource tab. You will have to provide a value for each resource in each activity.
No. I am not using any resource curves. I did some searching. There are some different things I can try.
Anything to do with resource curve type? Front loading or manual curve settings?