Hi:
My question is that, does Max Unit/Time link with any thing?
I am using
Max Units/Time = 2h/d
Price/Unit = 12/d
Default Units/Time = 8h/d
Duration = 10d
This gives me Budgeted Units = duration x Default Units/Time = 10h/d x 8d = 80h
When I assign this to activity with 10d duration the
laboure Cost comes with = Budgeted Units x Price/Unit = 80h x $12/h = $960 (for 10 days)
But where is Max Unit/Time which 2h/d ? Does this not link with any thing? Or my calculations are wrong?
Hi Amit
You have not Included Risk Anaylysis in You Blog?
Regards
Arian.
Hi Asim,
Max Units/Time is used for resource levelling and does not have any effect it Total Units calculation. If a resource can work only 8 hours a day and you assign it to multiple activties and total working hours exceed 8 then it will show over-loading. This is particularly helpful when you arre using labour resources.
Regards
Amit
Check out my blog on Primavera at http://www.primaverablog.in