Hi Guys,
I have been in stuck importing contractor's program for the last 3 days. I just moved to a new project. Anyway, i have been trying to import the contractor's programme however I am getting a totally different cost values. I checked the currency settings and all the settings are matching with the contractor's P6. I also checked the work time periods in the admin settings but it's just alright.
I am getting 20,000,000,000 instead of 410,000,000.
Thanks for the future replies :)
D Artagnan,
my first thought is indeed the currency. But you checked that.
then I wonder, what cost? labor, nonlabor, material, expenses or total cost.?
Has just the budget changed or also the actual and remaining?
Are the calenders equal?
How about the duration type, is that equal and how is it calculated when you change that?
you want to give more information?
Regards,
Arend
Hi Mike,
Thanks for the prompt reply.
That's what i thought so but I checked the settings in liue to the work periods and it's exactly the same from the contractor's settings.
I had encountered this before and was able to fix it but that was 2 years ago....
:)
Hi D Artagnan
The differential is 49/1 - seems like it might be hours per week.
Best regards
Mike Testro