Hi All,
I have a schedule prepared in MSP and I import it to P6 as an xml file. Durations of the tasks in the imported file appears in Original Duration
column (as expected). However, when I change the duration of a task in the Original Duration in P6, the bar in the Gannt Chart does not get longer
or shorter. It gets longer or shorter when I change the duration in the Remaining Duration column.
In fact the Original Duration and Remaining Duration update in Ms Project but after saving the MS File Project as XLM to import to Primavera P6 this
no longer works.
Its as if the calculation in P6 is disabled for this imported Project and I do not know where.
Because If i start a new project in P6 all works as usual and Original Duartion and Remaining Duartion up date automatically
Any ideas whats wrong?
thanks Katrin
BY UTKUL CIL: I found the answer in one of the previous posts in forum. "Link Budget and At Completion for not started activities" checkbox under "Projects window => Calculations Tab" need to be checked. the problem is solved then.
To Katrin: there are many posts on this forum that could have anserwed your question.
I use to tell people: RTFM..
Regards,
Arend