resource smoothening

S
Sunil Babu 👤 Member for 15 years 6 months

Hi friends,

Anybody please explain defference between resource smoothening and resource levelling

Regards.

Sunil

R
Ronald Winter 👤 Member for 23 years 5 months

Both operations involve delaying activity starts in order to better manage resources.  Resource leveling delays any activity that would cause a resource requirement in excess of a stated maximum for any given time period.  P6 can perform this function.

 

Resource smoothing does not concern itself with resource availability so much as it does the change in resourcing.  It attempts to delay activity starts so as to reduce or eliminate sudden resource build-ups or build-downs.  It attempts to assign a level resource requirement over time.  P6 does not have a function for resource smoothing.  P3 did have smoothing settings but this was not real resource smoothing either.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts